Plumbing for low pressure die cushions (models C, D,
MC and MD) includes the following components:
- Surge Tank with gauge, pop safety valve and drain cock
- Reducing Regulating Valve and Pressure Gauge
- System Drain Cock
All plumbing components used should be rated to the working air pressure
of at least 150 psi for low pressure die cushions. Special attention
should be given to make sure that plumbing is free of metal shavings
and other debris (for example from threading pipes) that can get inside
the die cushion piston-cylinder wall and destroy the bearing surface.
Die Cushion surge port is connected to the surge tank using pipe or
hose assembly. At the convenient point outside the press bed, cross
should be installed that gives additional two input/output points
into the plumbing for shop air input line (through the regulator/gauge
assembly) and system drain line. |
|
When two or more cushions are installed in the same
bed, they can be either tied into one air system or have independent
air systems. Die cushions have to be under one air system if they
have common pin pad or if the uniform system pressure has to be achieved
between independent cushions.
If they have separate air systems, cushion pressures can be set differently
thus achieving different tonnages. In such case general instructions
for single cushion plumbing should be followed. As an option connecting
line can be added in between surge tanks for each of the cushions
with the ball valve. When the valve is closed each cushion will have
different pressure, once opened valve will allow for uniform pressure
in all of the cushions connected.
When multiple cushions are connected to one surge tank, the surge
line size should increase as they join into one line (it is discussed
later in this section). |
|
Surge
tank is very important part of the die cushion system as it prevents
the air to build up to prohibitive pressure at the bottom of the work
cycle of the press. The larger the surge tank, the more constant ring
holding force will be throughout the work cycle.
Surge tank is not required for model D die cushions with standard
draws as they have enough internal surge volume. In this case only
regulator and gauge assembly, pop safety valve and drain cock have
to be installed. Pop safety valve should be mounted directly onto
the die cushion into the tapped surge line hole. Drain cock should
also be installed in the bottom of the piston to drain any accumulated
moisture inside the die cushion. However, if longer than standard
stroke is used on D style die cushions, surge tank must be installed
for proper and safe operation of the die cushion. |
|
Surge port is located either in the back or on the side
of the die cushion piston flange. Depending on the installation, it
can be also drilled in the bottom of the piston, if space inside the
press bed is limited. All cushion units are drilled and tapped for
the correct size surge line to handle the flow of air required. On
multiple units installations a reducing bushing for the correct size
is furnished to give the proper air flow for the entire installation.
The pipe sizes given below are the recommended sizes for cushion installation
consisting of one to six cushion units connected together. |
Surge Port Size |
Cushion Model & Size |
Number of Cushions |
1 |
2 |
3 |
4 |
5 |
6 |
C6 & D6 |
1/2 |
3/4 |
1 1/4 |
1 1/4 |
1 1/4 |
1 1/2 |
C8 & D8 |
1/2 |
3/4 |
1 1/4 |
1 1/4 |
1 1/4 |
1 1/2 |
C10 & D10 |
3/4 |
1 1/4 |
1 1/2 |
2 |
2 |
2 |
C12 & D12 |
3/4 |
1 1/4 |
1 1/2 |
2 |
2 |
2 |
C14 & D14 |
1 |
1 1/2 |
2 |
2 1/2 |
2 1/2 |
3 |
C16 & D16 |
1 1/4 |
2 |
2 1/2 |
3 |
3 |
X |
C18 |
1 1/4 |
2 |
2 1/2 |
3 |
3 |
X |
C20 |
1 1/4 |
2 |
2 1/2 |
3 |
3 |
X |
C22 |
1 1/2 |
2 1/2 |
3 |
X |
X |
X |
C24 |
1 1/2 |
2 1/2 |
3 |
X |
X |
X |
|
Surge Port Size |
Cushion Model & Size |
Number of Cushions |
1 |
2 |
MC8 |
3/4 |
1 1/4 |
MC10 |
1 1/4 |
2 |
MC12 |
1 1/4 |
2 |
MC14 |
1 1/2 |
2 1/2 |
MC16 |
2 |
2 1/2 |
MC18 |
2 |
3 |
MC20 |
2 |
3 |
MC22 |
2 1/2 |
4 |
MC24 |
2 1/2 |
4 |
|
Surge tank should be installed as close to the cushion
unit as possible to minimize the flow of air through surge lines.
The surge tank itself may be installed in either a horizontal or vertical
position as each surge tank has the required number of outlets to
make either of the installations. Surge tank should have the pop safety
valve, pressure gauge and drain cock installed. These components are
furnished with each die cushion. For easy access, street elbow, nipple
and coupling (1/4" NPT) can be installed on the bottom of the
tank and then drain cock can be attached to them. |
|
Description |
Part Number |
Connection |
Pop Safety Valve 125 psi |
285 |
3/8 NPT |
Pressure Gauge |
284 |
1/4 NPT |
Surge Drain Cock |
443 |
1/4 NPT |
|
Regulator and Gauge assembly regulates the shop air
pressure and allows using die cushions at pressures lower than the
shop air one. High pressure hoses should be used from the regulator
to the cushion unit/cross when installing this assembly. A brass or
steel pipe may be used, however, a high pressure hose is long-lived
and absorbs the shock of the press on the regulator and gauge. Another
hose should be used on the input side of the regulator to connect
it to the shop air line that should be pipes within 2 to 2 1/2 feet
of the pressure regulator. It is also advisable to install a globe
valve and air filter on the end of the pipe so that air pressure can
be turned off when cushion is not in use and only clean, free of debris
air is delivered to the die cushion. The regulator and gauge assembly
comes with a bracket and should be installed on the side of the press
approximately 5-6 ft from the flow within easy reach and view of the
operator.
After the globe valve has been attached to the shop air line, be sure
to blow out the shop air line to remove any foreign matter or dirt
before connecting the short length hose from the globe valve to the
inlet side of the pressure regulator. If this precaution is not taken,
there is a possibility that a small piece of dirt will get under the
seat of the regulator valve and it will not function properly. Also,
note that the regulator openings are marked with arrow to indicate
direction of flow so that air hoses can be connected to the correct
side for proper operation. |
Description |
Part Number |
Connection Size |
Regulator Assembly |
1502 |
x |
Regulator |
3241 |
1/4 NPT |
Pressure Gauge |
284 |
1/4 NPT |
Vibration Dampers |
451 |
x |
Hose Assembly |
3248 |
x |
3 ft Hose |
6310 |
1/4" |
6 ft Hose |
6309 |
1/4" |
Hose Adapters |
6313 |
1/4" NPT |
Globe Valve |
Not Furnished |
x |
Air Filter |
Not Furnished |
x |
|
|
System drain is important part of the die cushion plumbing.
It allows removing all accumulated moisture inside the die cushion
that can limit the surge volume and cause the increased system pressure
(above allowable levels) at the bottom of the working stroke. That
is why drain cocks should be opened regularly as a part of the die
cushion maintenance schedule. Usually die cushion installation should
have 2 drains installed, one at the low point of plumbing and the
other one directly on the tank. To create the entry port for the second
drain cock mentioned, cross and reducing bushing is shipped with die
cushion. It should be installed outside the press so that there is
easy access to the drain cock. The other open port on the cross should
be used to connect high pressure hose from the regulator. |
|